25 March 2026 Progress Update on the GRDM Regional Waste Management Facility Construction

Progress Update on the GRDM Regional Waste Management Facility Construction

Update 2

Construction full steam ahead.

The contractor, Civils 2000, appointed for the construction of Phase 1 of the Regional Waste Management Facility, is progressing well. The recent severe weather conditions raised concerns about potential damage and delays; however, the contractor had put measures in place to minimise any impact. No serious damage was reported, and the contractor remains on track with the construction programme despite the adverse conditions.

Construction is approximately 33% complete, and the completion date remains set for 24 February 2027.