30 September 2025 Update 10 – Gwaiing Road Construction Works, George

Update 10 – Gwaiing Road Construction Works, George

The upgrading of the Gwaiing Road between the R404 and the R102 remains the focus of the GRDM Road Construction Team.

The right hand side (RHS) lane has since been primed with a bituminous prime. The lane still remains closed to traffic as this is a preparation layer for the final seal.

Testing has been done on the surface of the primed layer, to finalise the application rates for the final seal. Once the design has been approved, the final seal will be placed on the lane. This operation will occur over a 4 day period with ideal weather conditions, after which the traffic will be shifted to the completed RHS. This will then allow for the continuation and completion of the construction of the left hand side lane.

The Concrete Section remains in the process of completing the concrete-lined side drains.

Completion date of the project still remains at 31 January 2026, with the progress standing at 85%.