03 May 2024 Update: Gwaiing Road Construction Works, George
Update: Gwaiing Road Construction Project
03 May 2024
The Gwaiing project is still in its construction phase with the progress of the project currently stands at 78% works completed.
The Road Construction team is currently busy with the cement stabilisation of the subbase layer on the RHS lane, which is the second to last layer that will be placed on the newly constructed road, after which, the construction of the final Basecourse layer will begin.
The main focus areas at this stage remain the processing of the layer works. Material is still being carted in from the approved source. The drainage network on the entire section of road has been improved, with minor concrete structures currently being constructed for erosion control.
The intended final completion date is set for 18 September 2024.
-ENDS-