05 April 2024 Update: Gwaiing Road Construction Works, George

Update: Gwaiing Road Construction Project

05 April 2024

The Gwaing project is still in its construction phase.  The progress of the project currently stands at 70% works completed, after a few rain delays were experienced in the last two weeks.

The main focus areas at this stage remains the processing of the layer works. Material is still being carted in from the approved source, with the cement stabilisation process scheduled to start as early as next week. The drainage network on the entire section of the road has been improved, with minor concrete structures currently being constructed for erosion control.

The intended final completion date is set for 18 September 2024.

-ENDS-