04 March 2026 Update 14 – Gwaiing Road Construction Works, George
Update 14 – Gwaiing Road Construction Works, George
04 March 2026
The road project is anticipated to be completed by the end of March 2026.
The project incurred some delays as a result of the recent rainfall which delayed the curing and drying process of the layerworks.
The final gravel layer on the left hand side (LHS) lane has been processed and the team is awaiting the laboratory test results of the soil samples taken. As soon as the layer is approved, the final bituminous seal is ready to be placed on the lane. Once the LHS lane has been sealed, the road markings will be painted and all road signage will be erected.
The Concrete team is in the process of completing all concrete works on the site, and the final shaping of the road shoulders are also in progress.