Progress Update 4 on the GRDM Regional Waste Management Facility Construction
Progress Update 4 on the GRDM Regional Waste Management Facility Construction
3 August 2026
“The construction of the Garden Route District Municipality’s Regional Waste Management Facility, located 15km outside Mossel Bay next to PetroSA, remains on schedule,” said Johan Gie, Manager: District Waste Management.
This facility will provide a long-term waste disposal solution for participating municipalities across the Garden Route. With landfill airspace in the region becoming increasingly limited and waste volumes continuing to grow, the need for this project has never been greater.
The facility is being developed to reduce environmental risks, protect our groundwater and ensure waste is managed responsibly for the benefit of future generations.
Construction is progressing well across several key components of the project.
Behind me is Cell 1A, the first engineered landfill cell. It is being lined with specialised lining materials to prevent contamination of the surrounding environment, water courses, and groundwater. Once completed and approval for commencement of waste disposal is received, this will become the facility’s first operational disposal area.
Work is also progressing on the leachate and contaminated water dams, which will safely collect and store leachate and rainwater that has come into contact with waste, preventing any harmful impact on the environment.
The office block will serve as the administrative hub for the facility, while the weighbridge office will accurately record every vehicle entering and leaving the site to support efficient landfill management and waste disposal data management.
Construction of the workshop, perimeter fencing and concrete access roads is also underway, ensuring the facility is secure, well maintained and operates efficiently.
According to Johan Gie, “the project is being constructed by Civils 2000 at a contract value of R109 million, with completion expected towards the end of February 2027”.
While construction continues, every resident can also make a difference by reducing waste, recycling and participating in source separation programmes within their local municipality.