31 October 2025 Update 11 – Gwaiing Road Construction Works, George
Update 11 – Gwaiing Road Construction Works, George
Upgrading of the Gwaiing Road between the R404 and the R102 remains the focus of the Garden Route District Municipality Roads Construction Team.
During the month of October, a triple seal has been completed in full on the right hand side (RHS) lane of the project, which brings the construction of the RHS to completion. Traffic has since been redirected to the completed RHS lane as the construction operations are now directed to the left hand side (LHS) lane. The next phase in construction on the LHS lane is the cement stabilisation of the subbase layer, which will commence at the beginning of November.
The concrete team remains focused on the completion of the concrete lined side-drains, as well as constructing of the concrete edge beams at all accesses along the road.
Completion date of the project still remains at 31st January 2026, with the progress standing at 87%.
ENDS